首页--工业技术论文--建筑科学论文--地下建筑论文--市政工程论文--给水工程(上水道工程)论文

尼泊尔达兰供水项目管理研究

Abstract第4页
摘要第6-13页
CHAPTER ONE:INTRODUCTION第13-17页
    1.1 Background of the Subject第13页
    1.2 Significance of The Subject第13-14页
    1.3 Purpose of the Study第14页
    1.4 Scope of the Study第14-15页
    1.5 Research content and structure第15-17页
CHAPTER TWO:LITERATURE REVIEW第17-27页
    2.1 Introduction第17-18页
    2.2 Cost management第18-21页
    2.3 Time management第21-24页
    2.4 Quality management第24-27页
CHAPTER THREE:RESEARCH SURVEY AND INTRODUCTION AND PRESENTAION OFDHARAN WATER SUPPLY PROJECTS第27-61页
    3.1 Goals and description of samples第27-32页
    3.2 Summary of case studies第32页
    3.3 Introduction and presentation of dharan water supply project第32-55页
        3.3.1 Delineation of service area and population coverage第32-34页
        3.3.2 Layout and engineering design第34-35页
        3.3.3 Multiple distribution zones/dma第35-37页
        3.3.4 Water source第37页
        3.3.5 Water quality assessment第37-38页
        3.3.6 Transmission mains / Pumping Mains第38-40页
        3.3.7 Distribution reservoirs第40-41页
        3.3.8 Distribution mains第41-42页
        3.3.9 Bulk meters and other valve chambers第42页
        3.3.10 Thrust blocks/anchor blocks第42-43页
        3.3.11 River/Stream crossing第43-44页
        3.3.12 House connections/shared taps第44-45页
        3.3.13 Electromechanical components第45-50页
        3.3.14 Other system appurtenances第50页
        3.3.15 Road reinstatement works第50-51页
        3.3.16 Project cost estimate第51-55页
    3.4 Operation and management第55-61页
        3.4.1 General第55-56页
        3.4.2 Personnel Cost第56-57页
        3.4.3 Maintenance cost第57页
        3.4.4 Total operation and maintenance cost第57-58页
        3.4.5 Operation by contractor第58-59页
        3.4.6 Cost of operation by contractor第59-61页
CHAPTER FOUR: PROBLEMS ON DHARAN WATER SUPPLY PROJECTS第61-79页
    4.1 Problems investigation by Comparing with other four related projects importance of factors ofvariance第61-69页
        4.1.1 Problem investigated Comparing Dharan water supply project with Kathmandu water supplyproject as below第61-63页
        4.1.2 Problem investigated Comparing Dharan water supply project with melamchi water supplyproject as below第63-65页
        4.1.3 Problem investigated Comparing Dharan water supply project with BHakundebeshi watersupply project as below第65-67页
        4.1.4 Problem investigated Comparing Dharan water supply project with Damak water supplyproject as below第67-69页
    4.2 Problem investigation by Comparing research projects actual situation with expected plan第69-77页
        4.2.1 Problem investigation of causing cost overrun in Dharan water supply project第74-76页
        4.2.2 Problem investigation of causing time overrun in Dharan water supply project第76-77页
    4.3 Summary of problem investigation by comparing other related projects and Dharan watersupply project actual situation with expected plan第77-79页
CHAPTER FIVE:PRESENTATION OF FACTORS CAUSING COST AND TIME OVERRUNAND THEIR RELATIVE IMPORTANCE第79-139页
    5.1 Factors influencing cost overruns at researched project第79-90页
    5.2 Factors influencing time overruns at construction projects第90-134页
    5.3 Degree of agreement among the Owners, Contractors, and Consultants for time and costoverruns groups第134-139页
CHAPTER SIX:SUGGESTION AND COCLUSIONS第139-149页
    6.1 Suggestion to Contractors第139-140页
    6.2 Suggestion to Owner第140-141页
    6.3 Suggestion to Consultants第141页
    6.4 Suggestion to Government第141页
    6.5 Conclusions第141-149页
REFERANCES第149-153页